Alaoji’s 450MW Return After Three Years Sparks Hope For Stable Power

0
LAGOS – On Thursday, the 450-megawatt Alaoji Open Cycle Power Plant in Abia State roared back to life after a three-year shutdown caused by disparities between metering and trading points – a billing dispute.
During the three year inactivity of the plant, debts also accumulated amid unresolved dispute, while the pipeline feeding the plant had faults that needed remedial works.
The plant had earlier endured temporary suspensions, including prolonged force majeure events resulting from vandalism on major feed gas pipelines like the Northern Option Pipeline.
Apart from the stagnant dispute during the period, the plant also recorded zero generation for 36 months and negatively impacted the economy of South-East Nigeria.
Sadly, Aba manufacturers / Distribution company lost a potential 450MW of power. The Nigerian Electricity Regulatory Commission data of first quarter of 2024, also confirmed that the plant generated zero electricity in six months during the period, highlighting the degree of its idleness.
Stakeholders say the return of the 450MW Aba Plant being managed by the Niger Delta Power Holding Company (NDPHC) is a boost for the country’s erratic grid system which has lately caused national embarrassment on account of frequent blackout.
They also say the restoration of the plant came at the right time Nigeria needed stable grid and increased electricity to power its industrialization drive in line with the Renewed Hope Agenda of President Bola Tinubu administration.
PATH TO REVIVAL
At a recent meeting to the governor of Abia State, Alex Otti, the Managing Director and Chief Executive Officer of the Niger Delta Power Holding Company (NDPHC), Engr. Jennifer Adighije, briefed her host on efforts being taken by her company to resuscitate the power plant for national use.
She told the governor that the plant’s shutdown was further compounded by outstanding financial obligations, but she was not deterred by the inherent challenges to put the plant in good shape.
She hinted that the restoration of the Alaoji plant became a top priority when she occupied the driver seat of the NDPHC in 2024.
She said: “The good news is that we have completed all remedial works on the defective gas line. We have also fully defrayed our outstanding obligations to TotalEnergies, and gas supply to the plant has now been restored.”
She added that extensive electromechanical works had also been carried out on the plant, resulting in the successful restoration of three generating units: GT1, GT22 and GT23 which are now available to dispatch about 375 megawatts of electricity to the national grid.
She noted that the plant possesses adequate transmission infrastructure with no significant evacuation constraints, describing it as a strategic and viable generation asset capable of supporting improved electricity supply nationwide.
The NDPHC boss also lauded the Abia State Government for its reforms in the electricity sector, particularly the Aba ring-fenced power arrangement and the establishment of the state electricity regulatory agency.
She said the company was leveraging the provisions of the Electricity Act and the evolving bilateral electricity market to partner with states and eligible customers in improving electricity access across the country.
“We would love to form a strategic alliance with Abia State, considering your administration’s strong commitment to securing uninterrupted electricity supply for the people of the state,” she said.
IMPACT ON ABIA ECONOMY
Governor Otti commended the management of NDPHC for restoring the Alaoji plant, saying the development was critical to economic growth and industrialisation in Abia State.
He said: “The last time I visited the Alaoji plant, it was regrettable that such huge capacity was lying idle. I am delighted to learn that the plant has now been brought back to life.”
He disclosed that the plant could eventually be expanded from its current capacity to 800 megawatts and later to about 1,100 megawatts, subject to the availability of funding.
He told his guest that electricity remains one of the most critical drivers of economic development and noted that his administration had prioritised investments in power infrastructure since assuming office in 2023.
The governor further announced that the state government had ring-fenced the Umuahia electricity market and entered into an agreement with the Enugu Electricity Distribution Company to acquire electricity distribution assets covering Umuahia and surrounding areas.
The state would require about 100 megawatts to service the eight local government areas under the Umuahia ring-fence, while investments in renewable energy and mini-grid projects were also ongoing, he said.
He implored the state Commissioner for Power to work closely with NDPHC officials on modalities for wheeling electricity from the Alaoji plant to Umuahia and other parts of the state.
He promised the NDPHC management of the state government’s support and urged the company to remain steadfast despite prevailing challenges in the power sector.
PARTICIPATION, COMMERCIAL NEGOTIATIONS
The Abia state government and the management of NDPHC have expressed intent to tie commercial partnership that would bring about reliable energy supply in the state, apart from the resuscitation of the Alaoji Power Plant.
Speaking after a tour of the facility, the Abia State Commissioner for Power and Public Utilities, Engr. Monday Ikechukwu, assured Adighije of the state government’s readiness to partner with NDPHC.
He said the state was prepared to commence commercial negotiations with the company, stressing that reliable electricity supply remains a major priority of the administration.
WHAT EXPERTS SAY
Experts told SUNDAY INDEPENDENT that the restart of the 450 MW Alaoji Power Plant in Abia State, a key National Integrated Power Project (NIPP) facility, represents a plus to the current drive to light up Nigeria and make power accessible to Nigerians.
They also said the revival of the power plant is a litmus test to the effectiveness of the NIPP facility in closing electricity gap in Nigeria.
They emphasised the need for the government to resuscitate similar NIPP facilities in the country with a view to putting them to maximal use in electricity value chain.
Rasheed Adeleke, an energy expert, believed that the revival of the Alaoji Power Plant was in order and would serve the intended purposes.
He told SUNDAY INDEPENDENT: “Rapid industrialization will return to the South-Eastern part of the country as Alaoji Power Plant returns. The return of the power plant also means the gradual death of youth restiveness and killings in the East, which will ultimately bring about robust economy.
“The impact will not be limited to the East alone, but also spread to other parts of the country because the return of the Alaoji Plant will woo more Nigerian investors and others outside the shores of the country.”
He advised the government to consider reviving other idle or non-functional NIPP facilities in the country in order to ensure stable electricity and promote robust economy in Nigeria.
Corroborating Adeleke’s position, another expert, Wale Sunmola, told SUNDAY INDEPENDENT that the return of the 450MW Alaoji Power Plant signals a paradigm shift in the management of power infrastructure in the country.
He cautioned the government against politicising the gesture and underutilizing the benefits it will offer the country’s power sector.
Above all, stakeholders agreed that the restoration of the 450 MW Alaoji Power Plant is a huge boost for Nigeria’s power sector which should be reasonably sustained and maintained.